(1) Content:
- Project Duration:
The duration of this project is 1,110 calendar days from the start date.
- Total Amount: NT$46,450,000
(2) Scope of Work:
The locations of this project are as follows: Wenhu Line stations, Muzha Depot backup control center (including maintenance workstation),Neihu Airport control center (including maintenance workstation), Hu-Jie main substation, ventilation shafts, etc.
(3) Summary of System Update Key Points:
Control center architecture diagram:
Station Broadcast Architecture:
- The design of the main control unit for the station broadcast includes dual network communication ports, allowing it to simultaneously receive control from both the existing Communication Integration Server (OCC IS) and the newly installed broadcast server.
- The OCC control room workstations will maintain their current functionality through the IS, allowing continued operation of station broadcasts with no changes to the relevant operating modes.
- Additionally, independent broadcast workstations will be installed at IA positions and in other locations for station broadcasting.
- The broadcast server will provide APIs or communication protocols, reserved for future integration with the IS when it is reset to CMFT.