(1) Content:
- Project Duration:
The duration of this project is 20 calendar days from the start date.
(2) Scope of Work:
- Project Content::External pipeline engineering
The project location is described as follows::Point-to-point connection between unit sites.
(3) Summary of System Update Key Points:
- Work Summary Overview::Supply, connection, installation, and testing of 3 kV cables and related equipment.